OCTA Central County Corridor Major Investment Study (CCCMIS) Update: Board Approves Open Houses and Next SWG Meeting Set for June 23
The open houses will take place in Garden Grove (northern segment of study area), Fountain Valley (central/southern segment) and Tustin (eastern segment).
As you are aware, the list of projects – along with policy, technical and public feedback – will serve to develop a recommended LPS, which, in turn, will be presented to the Board for final approval in August.
Consistent with policy direction, the open houses will consist of informational stations which will serve to:
Present background information on OCTA
Explain the purpose and need of the major investment study process
Communicate the existence of baseline and committed initiatives for central O.C., such as M2
Present the proposed list of projects resulting directly from the CCCMIS process
Request feedback on the proposed list of projects resulting from the CCCMIS process
Summarize the overall transportation benefits all of these projects are projected to produce when fully developed and implemented
For your information, please note the open houses are scheduled to take place as noted below.
June 16, 2010
5:00 -7:00 p.m.
Monroe Elementary School
City of Fountain Valley
June 17, 2010
5:00 -7:00 p.m.
Tustin Public Library
City of Tustin
Following the open houses, the study team will develop and present a draft recommended LPS to both the Stakeholder Working Group and Technical Working Group for their input. The recommendation will then be presented to the PAC for approval in July. The next SWG meeting will take place on June 23, 2010.
Stakeholder Working Group meeting on June 23, 2010